T1 Tower 18th floor slab & 6th floor brick work.1.8.18
T2 Tower 2nd floor started.1.8.18
T3 Tower 2nd floor brick work 5th floor slab 1.8.18
T4 Tower 6th floor started & GF brick work.1.8.18
S2 Tower 13th floor slab & 8th floor brick work. 1.8.18
S3 Tower 16th floor completed & 4th-5th floor brick work.
S4 Tower 17th-18th floor slab & 6th floor brick work.