Speed S2 Interior work Details as of September 14th, 2019

Dear Friends, 

Am pleased to share above as provide by CRM- Solitairian City, for your kind perusal.

Block Work – 18th Floor (100% Complete) 19th Floor Ongoing 
CPVC Work Toliet- 15th Floor (100% Complete)
Chaukhat Fixing – 11th Floor Completed
Plaster Inside – 7th Completed and 8th Floor Ongoing 
Electrical Conduting Work – 10th Floor (100% Complete), 11th Floor On-Going
Scaffolding- Complete for the entire tower